Krisala Aventis, Tathawade — Verified Buyer Due-Diligence Report
by Krisala Developers (Devsia Infracon LLP) · Tathawade, Pune
No litigation on record
Checked against court records at the time of our review. Records change, so confirm before you pay.
Possession: two different dates
- Builder’s target
- May 2030 (builder's own marketing promise — earlier than either registered RERA date; plan finances around the RERA dates below, not this one)
- MahaRERA committed date
- 21 Oct 2030 for Wing B (revised from an original 21 Jun 2030) and 30 Sep 2031 for Tower A (revised from an original 31 May 2031) — both phases have already moved their RERA date once, by four months, and each further extension needs fresh MahaRERA approval.
RERA P52100080336 (Wing B / Phase 1; registered 22 May 2025; Active) and PR1261012600932 (Tower A / Phase 2; registered 24 Jun 2026; Active),Verify on MahaRERA
About this project
About Krisala Aventis
Krisala Aventis is a wellness-led, 4-tower master plan on roughly 3.15 acres in Tathawade, on the Pune–Bengaluru Highway side of PCMC, built by Krisala Developers through the project entity Devsia Infracon LLP. Two of the four towers are MahaRERA-registered today and Active: Wing B / Phase 1 (P52100080336, 199 units, RERA completion 21 Oct 2030) and Tower A / Phase 2 (PR1261012600932, 155 units including 18 non-residential, RERA completion 30 Sep 2031); Towers C and D are named in the brochure but not yet registered. Both registered phases show no disclosed litigation and "No Records Found" for complaints and appeals on the MahaRERA portal, and both already carry full-height Commencement Certificates. Homes are offered in 2, 2.5 and 3 BHK configurations from 738 to 1,076 sq ft carpet, launching at roughly ₹93 Lacs to ₹1.35 Cr — a 4–6% premium over the Tathawade average, which is normal for a branded new launch with a full wellness amenity deck. The project sells itself on biophilic design, cleaner indoor air, low-VOC materials and a large English-style landscaped garden, and sits inside Pune's strongest micro-market for schools and IT access: under a kilometre to the Mumbai–Bengaluru Highway, about 4 km to the Wakad Chowk metro station and about 7 km to Hinjewadi Phase 1. The two things every buyer here must manage are PCMC's genuine, independently confirmed water shortage (alternate-day supply since 2019, with a further 10% cut ordered from 16 October 2026) and the builder's own track record: Krisala has a solid decade-plus delivery history in this exact micro-market, but a separate, Krisala-linked project, 41 Cosmo, is reported among Pune's most-complained-about MahaRERA projects and running materially late — a warning worth asking Krisala about directly, and worth re-verifying against the MahaRERA portal's own complaint record before relying on the specific numbers reported for it (see cons and builderLitigationSummary).
Pawar Nagar–Dattawadi, Tathawade (PIN 411033), on the Mumbai–Bengaluru Highway (NH 48) side of Pimpri-Chinchwad Municipal Corporation (PCMC) limits, Pune West. GPS 18.6314 N, 73.7463 E.
Property Engineer Verdict
Our score for Krisala Aventis across legal standing, builder record, livability, connectivity and value, with the buy, wait or walk-away call.
Free. One call from an advisor, never sold on.
Key facts
The facts that decide daily life
- Land parcel
- Approved layout land of 12,745 sq m under Wing B and 12,825.30 sq m (revised) under Tower A — together roughly 3.15 acres across the full 4-tower master plan, per the staff report. Recreational open space is recorded as 1,207.25 sq m (Wing B) and 1,796.65 sq m (Tower A) on the respective MahaRERA layouts.
- Towers
- 4
- Floors
- Wing B (RERA-sanctioned): 2 basements + ground + 2 podiums + 26 upper floors, 31 sanctioned floors total, 199 flats and 0 shops. Tower A (RERA-sanctioned): 2 basements + ground + 1 podium + 24 floors, 28 sanctioned / 25 habitable, 137 flats + 18 non-residential = 155 units. The developer's own brochure instead describes BOTH towers as 26 storeys with 2 basements + ground + 2 podiums — Tower A's actual MahaRERA filing does not match that brochure claim (one podium, not two; 24 upper floors, not 26). Get Tower A's current sanctioned plan before booking there. Towers C and D are named in the master plan but are not yet MahaRERA-registered; RERA today covers 354 of a portal-reported ~470 total units across all four towers, leaving roughly 115 units for C and D unaccounted for.
- Lifts per tower
- Not published in the available material — confirm lift count and capacity per tower, especially for the 26-storey Wing B towers, with the sales team before booking.
- Ceiling height
- Not published in the available material.
- Construction
- Not specified in the available material — ask for the structural system (RCC frame vs Mivan/aluminium formwork) and a specification sheet before booking.
- Balconies
- Not published in the available material.
- Dry balcony
- Not published in the available material.
- Parking per flat
- Not published in the available material — confirm per-configuration allocation with the sales team.
- Parking levels
- 2 basements plus podium levels, kept free of resident traffic per the project's "car-free podium" design; exact floor-by-floor allocation not detailed in the available material.
- Approach road
- 24 m DP road on the north boundary, 18 m DP road on the south boundary, per the staff report's survey read.
- Builder grade
- A Cat
- Construction funding
- Debt-funded via Aditya Birla Capital — a ₹50 Cr charge registered against each phase. Wing B's charge is recorded on CERSAI; Tower A's charge is not yet on CERSAI as of the report date.
- Construction progress
- Not published as a percentage. Wing B holds a full-height Commencement Certificate (all 31 floors, issued 3 Jul 2025 and 13 Jan 2026) and its Phase 1 unit sizes are reported sold out on third-party listings, indicating meaningful progress; Tower A's CC (3 Jun 2026) is more recent. Confirm the exact percentage complete with the site team.
Unit plans and prices
Pick a layout, see what it costs
738 sq ft carpet
- Quoted price
- Ask us
- All-inclusive
- Ask us
- Minimum down payment
- Ask us
Site visit
Pick a day to walk through
See Krisala Aventis with an advisor who has already read the legal file.
- An advisor calls to confirm the day and time
- No cost, and no obligation to book
- Your number goes to the builder only if you ask us to introduce you
Choose a day to continue.
Our read
What works, and what to weigh
Pros & cons
The strengths and the drawbacks we found, written as plainly as each other.
Free. One call from an advisor, never sold on.
Amenities
What comes with the address
- Rooftop infinity pool on the high-rise towers
- Biophilic gym
- Yoga and meditation zone
- Badminton court
- Pickleball court
- English landscape garden estate
- Car-free podium life — parking confined to 2 basements and podium levels
- Mixed tower heights: two 26-storey towers (A, B) and two planned 14-storey towers (C, D, not yet registered)
- 32+ total amenities listed in the project's RERA "Task Activities and Common Facilities" schedule — ask the site team for the complete list
- Biophilic design intent: cross-ventilation and natural daylight as stated design goals (brand claim — ask for documentation)
- Low-VOC interior materials pitched as part of the "guilt-free" wellness concept (brand claim — ask for a green-building certificate or material spec sheet)
- Detailed fixture, flooring and fitting specifications not published in the available material — request the specification sheet from the sales team
Location
Where Krisala Aventis stands
Approach road: 24 m DP road on the north boundary, 18 m DP road on the south boundary, per the staff report's survey read.. The wider the road to the society, the easier access stays as the area builds out.
- Mumbai–Bengaluru Highway (NH 48) service roadunder 1 km
- JSPM Rajarshi Shahu College campus, Jeevan Nagarabout 1 km
- DMart Tathawade / Rama Bizzbay (Property Engineer office)about 1.5 km
- Bhumkar Chowk, Wakadabout 2.5 km
- Dange Chowkabout 3 km
- Wakad Chowk metro station, Metro Line 3 (Pink Line)about 4 km
- Akurdi / Chinchwad railway stationsabout 5 / 6 km
- Pune International Airport, Lohegaonabout 23 km
Area growth
What is being built around it
Items marked Planned or In progress have not been delivered. Dates are the authority's or developer's, not ours.
Development plan and survey
- Zoning
- PCMC limits; Pimpri Chinchwad Municipal Corporation is the planning authority for both registered phases.
- Road reservations
- 24 m DP road on the north boundary, 18 m DP road on the south boundary, per the staff report's survey read — not independently re-verified against the sanctioned DP road-widening line.
- Future DP proposals
- NH 48 service-road widening to 12 m is underway; a planned 4-lane elevated corridor with a two-level flyover at Bhumkar Chowk and underpasses at Tathawade and Wakad remains at the planning stage and was reported stuck as of August 2026. PCMC's Draft Development Plan 2041 (finalised May 2025, roughly 50,000 objections filed, not yet sanctioned) will eventually reset roads, reservations and a High Capacity Mass Transit Route (HCMTR) for this ward — the HCMTR alignment has already drawn protests in Tathawade specifically.
- Survey numbers
- 155/3, 164/11, 164/12, 164/14, 165/1–6, 166/1, 166/6A, 166/6B, Plot 2, Pawar Nagar–Dattawadi, Tathawade (PIN 411033), PCMC limits — per the staff report. An independently found third-party listing for an "AVENTIS" project in Pawar Nagar–Dattawadi also names Devsia Infracon LLP as promoter, corroborating the location, though its own unit/acreage figures do not fully agree with ours (see cons).
- DP remarks
- Get the zone certificate and DP remarks for this project's specific survey numbers under both the current plan and the 2041 draft, and confirm no draft road widening, HCMTR alignment or public reservation touches the plot or its access roads before booking.
Before you book
What people ask us next
Maintenance
2 BHK: Not published in the available material · 2.5 BHK: Not published in the available material · 3 BHK: Not published in the available material
Payment plan
Not fully detailed in the available material
Documents
12 documents held on this project, shared with your free report.
Construction progress
Not published as a percentage. Wing B holds a full-height Commencement Certificate (all 31 floors, issued 3 Jul 2025 and 13 Jan 2026) and its Phase 1 unit sizes are reported sold out on third-party listings, indicating meaningful progress; Tower A's CC (3 Jun 2026) is more recent. Confirm the exact percentage complete with the site team. at our last check.
Rental income
2 BHK rents for about ₹22,300 – ₹28,000 a month semi-furnished. That is a gross yield near 3.2% on ₹93 L, an estimate before tax and vacancy.
Free download
Krisala Aventis buyer summary report
A short PDF with key facts, MahaRERA and possession checks, litigation on record, strengths and watch-outs. An advisor calls within 24 hours to take you through the full verdict — no obligation.
Project resources
Brochure & floor plans
The developer’s own material. We publish it as issued — read it alongside our analysis above, not instead of it.
See it
Walkthrough

Pricing intelligence
The quoted price is where the conversation starts.
Krisala Aventis is quoted at ₹93.00 Lacs – ₹1.35 Cr. Tell us where to reach you and we will send the closable price — plus how it stacks up against the projects around it.
- Comparative pricing against nearby projects, per square foot
- The price this project actually closes at, not the quoted one
- Backed by registered sale agreements from the last six months
Get the closable price
Free, and no obligation to buy through us.
One call from an advisor. Your number is never sold on.
Investment outlook
Appreciation & rental income
Appreciation & rental income
What this micro-market has appreciated at, and the rent a 2 or 3 BHK here actually commands.
Free. One call from an advisor, never sold on.
Handover
Possession & delivery
Build stage
Early Stage — Wing B structure topped out per its CC; Tower A newly registered (Jun 2026)
Builder's target
May 2030 (builder's own marketing promise — earlier than either registered RERA date; plan finances around the RERA dates below, not this one)
RERA committed date
21 Oct 2030 for Wing B (revised from an original 21 Jun 2030) and 30 Sep 2031 for Tower A (revised from an original 31 May 2031) — both phases have already moved their RERA date once, by four months, and each further extension needs fresh MahaRERA approval.
Construction complete
Not published as a percentage. Wing B holds a full-height Commencement Certificate (all 31 floors, issued 3 Jul 2025 and 13 Jan 2026) and its Phase 1 unit sizes are reported sold out on third-party listings, indicating meaningful progress; Tower A's CC (3 Jun 2026) is more recent. Confirm the exact percentage complete with the site team.
Construction funding
Debt-funded via Aditya Birla Capital — a ₹50 Cr charge registered against each phase. Wing B's charge is recorded on CERSAI; Tower A's charge is not yet on CERSAI as of the report date.
The developer is quoting May 2030 (builder's own marketing promise — earlier than either registered RERA date; plan finances around the RERA dates below, not this one), but the date it is legally committed to under RERA is 21 Oct 2030 for Wing B (revised from an original 21 Jun 2030) and 30 Sep 2031 for Tower A (revised from an original 31 May 2031) — both phases have already moved their RERA date once, by four months, and each further extension needs fresh MahaRERA approval. — 16 months later. Plan around the RERA date; the earlier one carries no penalty if it slips.
Due diligence
Legal & litigation
MahaRERA registration
P52100080336 (Wing B / Phase 1; registered 22 May 2025; Active) and PR1261012600932 (Tower A / Phase 2; registered 24 Jun 2026; Active),
Verify on the official MahaRERA portalLitigation status
Paperwork
Documents
Paperwork & documents
The title, approval and layout documents we hold on this project, and how to request copies.
Free. One call from an advisor, never sold on.
Developer
Builder profile
Krisala Developers (Devsia Infracon LLP)
Building since
About 2011–12, per the staff report (13+ years in Pune as of Dec 2025). Sagar Agarwal is independently confirmed as founder (Inc42); a stated Managing Director, Aakash Agarwal, could not be independently corroborated in this pass.
Years of experience
14
Total projects
16
Cities of operation
Pune, Pimpri-Chinchwad, Nagpur
Our builder grade
A Cat
Krisala Developers is a Pimpri-Chinchwad-based developer with roughly 13–14 years in Pune, concentrated under its "Krisala 41" brand in the Tathawade–Punawale–Ravet–Wakad–Hinjewadi corridor. By its own disclosed figures (December 2025) it has delivered 16+ projects totalling about 2.3 million sq ft, with 6.3 million sq ft under construction. Its two biggest current bets are both joint ventures: a 105-acre Hiranandani–Krisala township in North Hinjewadi, and a newly announced golf township with Hiranandani in Nagpur (October 2026), alongside a 63-acre NA-plot development in Vadgaon–Talegaon. Sagar Agarwal is independently confirmed as the company's founder; a stated Managing Director, Aakash Agarwal, could not be independently corroborated in this pass. The clearest caution on the record is a separate, Krisala-linked project, 41 Cosmo, reported as running materially late with a notable MahaRERA complaint count — the exact figures need re-verification directly on the MahaRERA portal, detailed in full in builderLitigationSummary.
Background
Krisala Developers is a Pimpri-Chinchwad-based developer operating in Pune for roughly 13–14 years, concentrated in the Tathawade–Punawale–Ravet–Wakad–Hinjewadi corridor under its "Krisala 41" brand. By its own disclosed figures (December 2025) the company has delivered 16+ projects, about 2.3 million sq ft completed and a further 6.3 million sq ft under construction. Its biggest current bets extend beyond its home turf: a 105-acre township joint venture with Hiranandani in North Hinjewadi (reported GDV around ₹7,000 Cr), a 63-acre NA-plot development (Land of Dreams) in Vadgaon–Talegaon, and a newly announced golf township with Hiranandani in Nagpur (October 2026). Within Tathawade specifically, the company's delivery record across 41 Cosmo NXT, 41 Earth, 41 Elite and several completed 41-series towers is solid, and Krisala Aventis's own Phase 1 sizes are reported sold out. The one clear warning in the record is a separate, Krisala-linked project, 41 Cosmo, reported as running materially late and carrying a notable buyer-complaint count on MahaRERA — though the exact registration number and complaint figure behind that claim could not be independently corroborated in this pass and should be re-verified directly on the MahaRERA portal before being relied on (see legalVerificationNotes). A single unverified public review (MouthShut, Jan 2024) on the separately delivered 41 Elite alleges plan changes and parking/STP issues; it is one person's account and unverified, but worth asking existing 41 Elite residents about directly. The seller entity for Aventis, Devsia Infracon LLP, is itself a project-specific company with no independent MahaRERA track record of its own — delivery here depends on the Krisala group behind it, which is itself expanding rapidly across townships, NA plots and a new city (Nagpur), a pace of growth that can stretch site teams and cash even for an otherwise solid regional developer.
15-year litigation search on the developer
No litigation is disclosed against Krisala Aventis itself on either registered phase, and `litigation` is set false accordingly — both P52100080336 and PR1261012600932 answer "No" to the litigation question and show "No Records Found" under Complaint Details and Appeal Details on the MahaRERA portal as of 3 Nov 2026. The wider Krisala group carries one clear warning, though it requires its own re-verification: our source report names a separate, Krisala-linked project, 41 Cosmo (Orange Krisala Realty LLP, cited there as registration P52100045292), as carrying 71 buyer complaints on MahaRERA, ranked #7 in Pune by complaint volume, and running about 11 months past its RERA date, citing a single secondary source (RERAdetails, 3 Nov 2026). Independent search in this pass could not corroborate that specific registration number or the complaint count — it surfaced two DIFFERENT 41-Cosmo-branded MahaRERA registrations instead (P52100029844, completed December 2024, 233 units; and P52100047695, on a different listing page), and no independent source stating a complaint figure or Pune-wide ranking. This does not mean the underlying warning is false — Krisala should be asked directly what caused any 41 Cosmo delay and whether buyer complaints are being settled — but the specific number and ranking should be read directly off the MahaRERA portal, under the correct registration, before being published as a numbered claim. Separately, a single unverified public review (MouthShut, January 2024) alleges plan changes, parking and STP issues at the separately delivered 41 Elite project; it is one person's account, unverified, and worth raising directly with existing residents rather than relying on. Our own 15-year civil and criminal search on Krisala Developers and its named promoters has NOT been run.
Other projects
Get the free Property Engineer report on Krisala Aventis
Title and approvals, DP and survey verification, a 15-year builder search, registered sale agreements from the last six months, and area growth analysis — written for you, not for the developer. No cost, no obligation.
Ask about this project
Questions
Krisala Aventis — buyer questions answered
The questions buyers actually ask about Krisala Developers (Devsia Infracon LLP) before paying a booking amount, answered from what we have checked on Krisala Aventis in Tathawade. Where we have not verified something, the answer says so rather than guessing.
Builder credibility, legal standing & approvals
The questions buyers ask before trusting a developer with a booking amount. Answered from what we have verified — and where we have not verified something, it says so.
Prices, possession & buying process
The practical detail on this project.